:: HOME :: YARRAM/DEVON NORTH :: PROJECTS :: 
   
 

brief development approval history

       

date

activity
 
documents
       
30.09.2004

A preliminary project presentation to Wellington Shire Council was held to ascertain the Council’s response to the possibility of a wind farm development on the intended site. The meeting was attended by eight people from Council including:

  • Mr. Jeff Amos, Mayor
  • Mr. John Jago, Councilor
  • Mr. Peter Gault, Councilor
  • Mr. Steven Dickson, Director Community and Economic Development
  • Ms. Heather Karl, Town Planner
  • Mr. John Roberts, Town Planner
  • Ms. Kim Phillips, Manager Development
  • Mr. Jason Pullman, Strategic Planner
  » Presentation Wellington Shire Council. PDF (464 KB)
02.03.2006 Development application submitted with Wellington Shire Council   » Planning and technical documents
27.10.2006 Refusal to grant a permit by Wellington Shire Council » Letter Wellington Shire of 27 October 2006. PDF (290 KB)
1-3.08.2007 VCAT hearing was held 1st, 2nd and 3rd August 2007 in Sale and 6 September 2007 in Melbourne   » VCAT Order of 04. April 2007. PDF (22 KB)
21.12.2007

VCAT Order:

  • The decision of the Responsible Authority is set aside. In permit application P73/2007 a permit is granted and directed to be issued for the land at 144 Ingles Road, Devon North.
» P2691 2006 Synergy Wind Pty Ltd v Wellington SC and Ors (jr ip 201207). DOC file (167 KB)
21.12.2007

Development Approval

  » Planning Permit Issued at the direction of VCAT. PDF (248 KB)